Assign Shift Schedule to Attendance Group

Assign Shift Schedule to Attendance Group

After setting the shift schedule, you need to assign it to the attendance group so that it will calculate the attendance records for persons in the attendance group according to this shift schedule.

Perform this task to assign a shift schedule to attendance group(s).

  1. Click Time & Attendance > Shift Schedule to enter the shift schedule management page.
  2. Enter the Assign to Attendance Group page.
    • After you set the parameters of shift schedule when adding, click Add and Assign.

    • When editing the shift schedule, click Configuration in the shift schedule details page.

    • Click in the Operation column.

  3. In the Assign to Attendance Group field, select the attendance group(s) you want to assign the shift schedule to.
    Note:

    Only the attendance groups which haven't been linked to a shift schedule will display.

  4. Optional: Click Add New to add a new attendance group.
  5. Click Save.

Assign Shift Schedule to Attendance Group

After setting the shift schedule, you need to assign it to the attendance group so that it will calculate the attendance records for persons in the attendance group according to this shift schedule.

Perform this task to assign a shift schedule to attendance group(s).

  1. Click Time & Attendance > Shift Schedule to enter the shift schedule management page.
  2. Enter the Assign to Attendance Group page.
    • After you set the parameters of shift schedule when adding, click Add and Assign.

    • When editing the shift schedule, click Configuration in the shift schedule details page.

    • Click in the Operation column.

  3. In the Assign to Attendance Group field, select the attendance group(s) you want to assign the shift schedule to.
    Note:

    Only the attendance groups which haven't been linked to a shift schedule will display.

  4. Optional: Click Add New to add a new attendance group.
  5. Click Save.